Stage 1 ActivitiesStage 2 ActivitiesStage 3 ActivitiesStage 4 Activities
PlannedCompletedPlannedCompletedPlannedCompletedPlannedCompleted
Entire Project 1443 695 1998 843 777 106 555 222
Batch I 351 235 486 168 189 27 135 54
Batch II 520 345 720 377 280 52 200 82
Batch III 572 115 792 298 308 27 220 86
ERID Total 676 295 936 377 364 34 260 102
Batch I 169 116 234 78 91 13 65 26
Batch II 221 128 306 154 119 12 85 32
Batch III 286 51 396 145 154 9 110 44
CRID Total 767 400 1062 466 413 72 295 120
Batch I 182 119 252 90 98 14 70 28
Batch II 299 217 414 223 161 40 115 50
Batch III 286 64 396 153 154 18 110 42